Habitat for Humanity of East King County: Construction Update, January 21, 2009

Construction Update, January 21, 2009

Patterson Park:
HVAC finished!
Fire sprinklers will be inspected next week.
Electrical inspection this week.
Siding continues.
Fire stopping continues.
Next week some trenching for gas, phone and cable begins.

Koinonia Ridge:
Unit #10
Sheetrock is up and first coat of mud is going on Saturday.
Continued with exterior paint.
Completed insulation in crawl space.

Unit #13
Siding and Mechanical rough-in continue

Unit #30
Started electrical process.
Continued caulking/spackling on exterior.
Worked on interior framing punchlist.

Unit s#32/ #33
Continued housewrap and window installation.

Unit #41
HVAC 50% complete.
Wired, insulated and sheetrocked furnace room.

SHEDS
Continued with siding trim.
Completed roof framing.
Started shingles on 6 unit shed.

Next Week:
Continue with exterior paint.
Siding on #13 and #41
Window and door installation on #32 and #33.
Wiring on #30.
Continue work on the homeowner sheds.