Construction Update, January 21, 2009
Patterson Park:
HVAC finished!
Fire sprinklers will be inspected next week.
Electrical inspection this week.
Siding continues.
Fire stopping continues.
Next week some trenching for gas, phone and cable begins.
Koinonia Ridge:
Unit #10
Sheetrock is up and first coat of mud is going on Saturday.
Continued with exterior paint.
Completed insulation in crawl space.
Unit #13
Siding and Mechanical rough-in continue
Unit #30
Started electrical process.
Continued caulking/spackling on exterior.
Worked on interior framing punchlist.
Unit s#32/ #33
Continued housewrap and window installation.
Unit #41
HVAC 50% complete.
Wired, insulated and sheetrocked furnace room.
SHEDS
Continued with siding trim.
Completed roof framing.
Started shingles on 6 unit shed.
Next Week:
Continue with exterior paint.
Siding on #13 and #41
Window and door installation on #32 and #33.
Wiring on #30.
Continue work on the homeowner sheds.
HVAC finished!
Fire sprinklers will be inspected next week.
Electrical inspection this week.
Siding continues.
Fire stopping continues.
Next week some trenching for gas, phone and cable begins.
Koinonia Ridge:
Unit #10
Sheetrock is up and first coat of mud is going on Saturday.
Continued with exterior paint.
Completed insulation in crawl space.
Unit #13
Siding and Mechanical rough-in continue
Unit #30
Started electrical process.
Continued caulking/spackling on exterior.
Worked on interior framing punchlist.
Unit s#32/ #33
Continued housewrap and window installation.
Unit #41
HVAC 50% complete.
Wired, insulated and sheetrocked furnace room.
SHEDS
Continued with siding trim.
Completed roof framing.
Started shingles on 6 unit shed.
Next Week:
Continue with exterior paint.
Siding on #13 and #41
Window and door installation on #32 and #33.
Wiring on #30.
Continue work on the homeowner sheds.