Construction Update, February 16, 2009
Patterson Park:
Insulation is ready for inspection on Tuesday.
Electricity is hooked up and the meters are set.
Gas meters are unlocked and turned on.
Soffits are 80% complete.
Siding closer to being complete.
All furnaces running properly.
Sheetrock is scheduled to be delivered this week.
Work this week: siding on roof, caulking, painting and decks.
Koinonia Ridge:
Unit #10
Millwork 90% installed and painted.
Cabinets complete.
Countertops - 75% built.
Electrical trim - 75% complete.
HVAC trim complete.
Installed toilets.
Insulated pipes in crawl space, water is on.
Unit #13
Electrical rough-in 80%, panel wired.
Siding complete.
Continued with exterior paint.
Framed front deck.
Worked on framing corrections.
HVAC completed and ready for re-inspection.
Unit #30
Iinsulation passed inspection.
Sheetrock is up and inspected.
Utilities should be connected this week.
Framed front deck.
Ordered interior doors and millwork.
Unit #32
Continued with 1st level of siding, 3 sides complete
Plumbing rough-in - 80% complete.
Unit #33
Installed housewrap over lower roof.
Installed two more windows.
Installed sheetrock and wiring for furnace room.
Unit #41
Completed siding on back of house.
Continued with exterior paint.
Started layout, drilling and installing boxes for electrical rough-in.
HVAC 90% complete, wall terminations will be installed after siding goes on.
Sheds are ready for homeowner use. Trim paint continues.
We had a professional painter volunteer this week. He painted all of the interior doors and all trim that was installed in #10. It looks amazing!
Next week we will continue with exterior painting, electrical rough-in on #13 and #41, countertops and millwork #10, and random siding. Possibly more decks as well.
Insulation is ready for inspection on Tuesday.
Electricity is hooked up and the meters are set.
Gas meters are unlocked and turned on.
Soffits are 80% complete.
Siding closer to being complete.
All furnaces running properly.
Sheetrock is scheduled to be delivered this week.
Work this week: siding on roof, caulking, painting and decks.
Koinonia Ridge:
Unit #10
Millwork 90% installed and painted.
Cabinets complete.
Countertops - 75% built.
Electrical trim - 75% complete.
HVAC trim complete.
Installed toilets.
Insulated pipes in crawl space, water is on.
Unit #13
Electrical rough-in 80%, panel wired.
Siding complete.
Continued with exterior paint.
Framed front deck.
Worked on framing corrections.
HVAC completed and ready for re-inspection.
Unit #30
Iinsulation passed inspection.
Sheetrock is up and inspected.
Utilities should be connected this week.
Framed front deck.
Ordered interior doors and millwork.
Unit #32
Continued with 1st level of siding, 3 sides complete
Plumbing rough-in - 80% complete.
Unit #33
Installed housewrap over lower roof.
Installed two more windows.
Installed sheetrock and wiring for furnace room.
Unit #41
Completed siding on back of house.
Continued with exterior paint.
Started layout, drilling and installing boxes for electrical rough-in.
HVAC 90% complete, wall terminations will be installed after siding goes on.
Sheds are ready for homeowner use. Trim paint continues.
We had a professional painter volunteer this week. He painted all of the interior doors and all trim that was installed in #10. It looks amazing!
Next week we will continue with exterior painting, electrical rough-in on #13 and #41, countertops and millwork #10, and random siding. Possibly more decks as well.