Habitat for Humanity of East King County: Construction Update, February 16, 2009

Construction Update, February 16, 2009

Patterson Park:

Insulation is ready for inspection on Tuesday.
Electricity is hooked up and the meters are set.
Gas meters are unlocked and turned on.
Soffits are 80% complete.
Siding closer to being complete.
All furnaces running properly.
Sheetrock is scheduled to be delivered this week.

Work this week: siding on roof, caulking, painting and decks.

Koinonia Ridge:
Unit #10
Millwork 90% installed and painted.
Cabinets complete.
Countertops - 75% built.
Electrical trim - 75% complete.
HVAC trim complete.
Installed toilets.
Insulated pipes in crawl space, water is on.

Unit #13
Electrical rough-in 80%, panel wired.
Siding complete.
Continued with exterior paint.
Framed front deck.
Worked on framing corrections.
HVAC completed and ready for re-inspection.

Unit #30
Iinsulation passed inspection.
Sheetrock is up and inspected.
Utilities should be connected this week.
Framed front deck.
Ordered interior doors and millwork.

Unit #32
Continued with 1st level of siding, 3 sides complete
Plumbing rough-in - 80% complete.

Unit #33
Installed housewrap over lower roof.
Installed two more windows.
Installed sheetrock and wiring for furnace room.

Unit #41
Completed siding on back of house.
Continued with exterior paint.
Started layout, drilling and installing boxes for electrical rough-in.
HVAC 90% complete, wall terminations will be installed after siding goes on.

Sheds are ready for homeowner use. Trim paint continues.

We had a professional painter volunteer this week. He painted all of the interior doors and all trim that was installed in #10. It looks amazing!

Next week we will continue with exterior painting, electrical rough-in on #13 and #41, countertops and millwork #10, and random siding. Possibly more decks as well.