Construction Update March 2, 2009
Mike Hammerquist’s update on what’s been happening at Patterson Park in Redmond:
We finished hanging drywall on Tuesday. We started corner metal and scrap out on Thursday and taping on Friday. I expect them to finish the living areas this week and start taping the garages. Texture and priming to follow.
Interior painting should start at the end of the week.
Decking will start this week and will continue until we are able to finish the painting above the decks.
There are a couple of areas we need to remove the siding and replace it with pieces that fit properly. Caulking continues.
The electrical trim was started and finished in the garages. We are now off temporary power for construction and are using garage and deck outlets for construction power. As soon as the taping is done in the garages, we will install the lights and switches. Electrical trim will start after we get the walls/ ceilings painted.
Work this week will include painting, caulking, siding repairs and decking.
Doug Copley’s update on what’s been happening at Koinonia Ridge in Snoqualmie:
Unit #10
Completed countertops.
Installed sinks and shower trim, plumbing trim 90% complete.
Continued with finish work, towel bars, mirrors installed.
Electrical trim 90% complete.
Framed rear deck, stairs and guardrails remain.
Hand graded rocks, ready for landscaping.
Gutters installed.
Unit #13
Drywall is up.
Permanent electric installed, gas service will be installed on Monday.
Framed one rear deck.
Unit #30
Textured, painted interior walls.
Installed underlayment and vinyl flooring.
Cabinets will be installed this week.
Interior doors and millwork should arrive late this week.
Gutters installed.
Unit #32
Installed trim around first floor windows, started trim for 2nd level of siding.
Plumbing rough-in 80% complete.
HVAC rough-in 75% complete.
Primed siding.
Unit #33
Installed more hardi panel- 80% complete.
Installed siding over lower main roof- 75% complete.
Continued with trim around windows and doors.
Primed siding.
Unit #41
Continued electrical work- 90% complete (panel and phone and cable remain.)
Roofing is scheduled to be finished this week.
This week we will continue siding on Units #32 and #33, have inspections on Unit #41 and will insulate and continue work on the decks and hopefully continue interior work on Unit #30. Unit #13 should be ready to paint interior walls by the end of the week. We will also work on the storage yard and start some new site work.
We finished hanging drywall on Tuesday. We started corner metal and scrap out on Thursday and taping on Friday. I expect them to finish the living areas this week and start taping the garages. Texture and priming to follow.
Interior painting should start at the end of the week.
Decking will start this week and will continue until we are able to finish the painting above the decks.
There are a couple of areas we need to remove the siding and replace it with pieces that fit properly. Caulking continues.
The electrical trim was started and finished in the garages. We are now off temporary power for construction and are using garage and deck outlets for construction power. As soon as the taping is done in the garages, we will install the lights and switches. Electrical trim will start after we get the walls/ ceilings painted.
Work this week will include painting, caulking, siding repairs and decking.
Doug Copley’s update on what’s been happening at Koinonia Ridge in Snoqualmie:
Unit #10
Completed countertops.
Installed sinks and shower trim, plumbing trim 90% complete.
Continued with finish work, towel bars, mirrors installed.
Electrical trim 90% complete.
Framed rear deck, stairs and guardrails remain.
Hand graded rocks, ready for landscaping.
Gutters installed.
Unit #13
Drywall is up.
Permanent electric installed, gas service will be installed on Monday.
Framed one rear deck.
Unit #30
Textured, painted interior walls.
Installed underlayment and vinyl flooring.
Cabinets will be installed this week.
Interior doors and millwork should arrive late this week.
Gutters installed.
Unit #32
Installed trim around first floor windows, started trim for 2nd level of siding.
Plumbing rough-in 80% complete.
HVAC rough-in 75% complete.
Primed siding.
Unit #33
Installed more hardi panel- 80% complete.
Installed siding over lower main roof- 75% complete.
Continued with trim around windows and doors.
Primed siding.
Unit #41
Continued electrical work- 90% complete (panel and phone and cable remain.)
Roofing is scheduled to be finished this week.
This week we will continue siding on Units #32 and #33, have inspections on Unit #41 and will insulate and continue work on the decks and hopefully continue interior work on Unit #30. Unit #13 should be ready to paint interior walls by the end of the week. We will also work on the storage yard and start some new site work.