The latest from Mike Hammerquist, Construction Supervisor at the Issaquah Highlands:

Units 1A & 1B waiting for engineer to approve truss design. Currently scheduled for delivery 12 Jan. Building stairwell walls.

Unit 2A waiting for engineer to approve truss design. Currently scheduled for delivery 15 Jan. Building stairwell walls.

Unit 2B waiting for party wall inspection, then build other half of interior walls.

Work this week will include framing stairwell walls, interior walls, exterior sheeting, seismic hardware, and firring out basement stair walls.


From Doug Copley, Construction Supervisor at Koinonia Ridge in Snoqualmie:

Trusses are coming tomorrow for Lot #40. The job offices are gone and we now have an excavation and footing formed. We'll be pouring concrete on Thursday at 1:00 PM. The new trailer is ...cozy. I was able to hook the phone service back up but we are still running off of an extension cord for power. Hopefully we'll be able to get permanent power installed within two weeks.