Habitat for Humanity of East King County: Construction Update April 19, 2010

Construction Update April 19, 2010

Update from Mike Hammerquist, Site Supervisor at the Issaquah Highlands:

Unit #1:
Plumbing rough-in continues - 80% complete.
Side sewer hookup - 95% complete.
Siding progresses well.
HVAC install started Friday.
Gas install last Wednesday.

Unit #2:
Plumbing rough-in scheduled to start Monday.
Side sewer hookup will be put together on Tuesday/Wednesday.
Siding progresses well.

Work this week will include siding, caulking, painting (weather permitting), trench backfill, and maybe electrical rough in.

Update from Doug Copley, Site Supervisor at Koinonia Ridge in Snoqualmie:
Unit #40:
Finished installing laminate on countertops.
Plumbing trim- 50% complete.
Pouring sidewalks and driveway next Wednesday or Thursday.
Installed towel bars, miscellaneous touch ups.

Unit #42:
Continued with siding.
Lower hardi panel complete.
Middle hardi panel- 50% complete.
Upper T1-11- 50% complete.
Continued pre-painting/ priming.
Continued exterior caulk and spackle.
Roofing delivery scheduled for Monday, roofing installation should begin Tuesday.